Case study · Helping industry · 2019

Precycle: sorting building waste before it gets contaminated

A South Australian circular economy case study Rawtec worked on. 2019.

Summary published

A skip bin on a building site collects everything, which means it recycles almost nothing. Business as usual on a residential build diverts about 10% from landfill.

Precycle changed the timing rather than the sorting. Materials get collected at set stages during construction, while they are still clean and separated, before the next trade contaminates them.

Landfill diversion went from 10% to 76%.

76%

Landfill diversion, against 10% business as usual

3.8 to 1.1

Skip bins per house

15 to 4.5 m³

Waste volume per house

1.4 t

CO2 avoided per site

What the trial showed

Fewer bins, less volume, more recovered

Skip bins per house fell from 3.8 to 1.1 and waste volume from 15 to 4.5 cubic metres. Landfill diversion rose from 10% to 76%. The service runs across six stages with pick-up on demand within 48 hours, and material is checked both at collection and at unloading.

The environmental numbers per site

1.4 tonnes of CO2 avoided, 19.7 gigajoules of energy saved and 4.1 kilolitres of water saved. Across ten houses that is roughly the annual emissions of 3.1 cars and the annual electricity of 3.8 households.

It costs less than the bins it replaces

The model works because multiple skip bin removals cost more than staged collection. Site safety improves, illegal dumping drops, and the material is worth something because it is clean.

The market is 8,000 to 12,000 homes a year

South Australia builds between 8,000 and 12,000 homes annually. A typical residential project runs 12 to 18 weeks, which is what makes staged collection practical.

Rossdale Homes was the trial partner

The builder reported environmental benefits plus better site amenity and material management, which is the part that actually persuades other builders.

What it depends on

SOMEWHERE FOR THE MATERIAL TO GO

The model only works if recycling outlets will take clean, sorted streams. Contamination is what kills construction recycling, and this is a scheme designed entirely around avoiding it.

BUILDERS CHOOSING ECONOMICS OVER CONVENIENCE

One bin for everything is easier. Staged collection needs the builder to prioritise the cost saving over the convenience.

ROOM TO GROW

The service started with a 150 tonne a year limit, later removed. The case study suggests expanding across the South Australian construction sector and setting up a resource bank for reusable materials.

Related reports

Other pilots and case studies.

The full case study covers the six collection stages.

Working on something like this?

Most of our projects start with someone inside an organisation who already knows what needs to change and needs the evidence to back it in. If that is you, we would like to hear from you.